When you guys hire subcontractors, or if you work as a sub contractor - you charge for everything you do correct?

By this I mean, installing gutter apron, drip edge, ridge cap, starter shingles , etc.

I hear of some guys who don't and I am actually sort of surprised. Is it normal to charge ONLY by the square?


Top
 Profile  
 
  Post subject:
PostPosted: Fri Oct 01, 2010 2:28 am 
Offline
User avatar

Joined: Tue Dec 09, 2008 5:36 am
Posts: 2002
Images: 8
Location: Tulsa, Ok
Post liked: 124 times
Liked posts: 64 times
around here, the per square price includes pipe flashings, any vents, and step flashing. building a cricket, or massive amounts of custom flashing is extra.

some crews include nails, button caps, and caulk with the "per square" price too.

_________________
-Jason

Good work isn't cheap, and cheap work isn't good.


Top
 Profile Personal album  
 
  Post subject:
PostPosted: Fri Oct 01, 2010 4:33 am 
Offline

Joined: Thu Jul 23, 2009 4:13 am
Posts: 2321
Images: 14
Post liked: 281 times
Liked posts: 582 times
I have seen a number of variations but never where the labor charge was by the square regardless of the roof geometry. In most cases, we pay for steep, double steep, high, 2nd layer, ridge vent, chimney flash, skylights, etc.. In other words, in general, if we get paid a line item in the insurance scope, we pay the crew for doing it.

This seems to make sense to me. First, seems fair. Second, if the crew were only paid by the square, I'd have concerns about them taking shortcuts on items we didn't pay for. Unfortunately, the unpaid items that could be shorted are the areas where it may be most likely that leaks could occur down the road. Given we offer a 5 Year Workmanship Warranty, it would seem insane to try to save money now to only end up paying out much greater sums down the road.


Top
 Profile Personal album  
 
  Post subject:
PostPosted: Fri Oct 01, 2010 9:32 pm 
Offline

Joined: Sat Apr 24, 2010 11:11 pm
Posts: 567
Images: 1
Location: Richmond, VA
Post liked: 15 times
Liked posts: 28 times
Nearly all of my subcontract experience is lump sum. It really is about the only way I like to do anything. I look at the job and give them a labor price. Often I will provide materials too. I find it makes it easier on both parties.

_________________
www.larocheconstruction.net


Top
 Profile Personal album  
 
  Post subject: Authentic_Dad
PostPosted: Sun Oct 03, 2010 3:31 pm 
Offline

Joined: Mon Mar 09, 2009 1:30 am
Posts: 134
Post liked: 0 time
Liked posts: 0 time
Thats the way subcontractors needs to be paid....ofcourse me when am doing a job of mine own sale or subcontract will always make sure i do what its needed to prevent any water problems in the future, am one of those guys that hates going back and doing a repair........back to the extra pay for flashing, replacement of wood, this are extras that take time and if roofers dont get paid for it they will only use a pc. of metal and go over the broken boards......DAD i need to work for you..


Top
 Profile  
 
  Post subject:
PostPosted: Tue Oct 05, 2010 11:52 am 
Offline
User avatar

Joined: Sat Nov 28, 2009 8:21 am
Posts: 1158
Images: 0
Location: Kamloops, BC, Canada
Post liked: 96 times
Liked posts: 109 times
I would charge by the sq, and as Agape said, a lot of stuff would be included in the "square". Installing underlay, flashings around protrusions, a minimal amount of step/wall flash and normal caps.
Things I would charge extra for would be building anything, cutting any wood, skylights, ridge vent.

And it would be either I supply nothing at all, or everything I'll need to do the job.

_________________
Almost 100 years ago, injured workers rights were taken away, it's high time we got them back.


Top
 Profile Personal album  
 
  Post subject: Re: Authentic_Dad
PostPosted: Tue Oct 05, 2010 12:55 pm 
Offline
User avatar

Joined: Tue Dec 09, 2008 5:36 am
Posts: 2002
Images: 8
Location: Tulsa, Ok
Post liked: 124 times
Liked posts: 64 times
Abel wrote:
...DAD i need to work for you..




Me too!!!

_________________
-Jason

Good work isn't cheap, and cheap work isn't good.


Top
 Profile Personal album  
 
  Post subject:
PostPosted: Tue Oct 05, 2010 2:00 pm 
Offline

Joined: Wed Jan 21, 2004 6:39 pm
Posts: 1096
Location: Stillwater, MN
Post liked: 1 time
Liked posts: 13 times
Most of the subs in my area are from Mexico and charge a flat per square rate. They may get a little more for steep roofs though.

From what the insurance pays on average for labor to what they get on average for labor it's about 1/4-1/5.


Top
 Profile  
 
  Post subject:
PostPosted: Tue Oct 05, 2010 6:28 pm 
Offline

Joined: Mon Aug 23, 2010 4:53 pm
Posts: 141
Location: Ohio
Post liked: 0 time
Liked posts: 0 time
We have our own employees, but do have a side sub staff. We keep them busy. We pay $75.00 per sq., $7.00 per lf chimney flashing, $15.00 per sheet wood decking, we buy all materials and disposal. On larger jobs, 60+ squares and walkable, we pay out $70.00 per sq. I have a sub doing a 67sq, 10/12 roof right now and am paying $110.00 per sq. I have been using this sub for 6 years and have never had a call back. And the main guy drives 1 of my trucks.


Top
 Profile  
 
  Post subject:
PostPosted: Thu Oct 07, 2010 1:47 am 
Offline

Joined: Mon Mar 09, 2009 1:30 am
Posts: 134
Post liked: 0 time
Liked posts: 0 time
PTROOFING wrote:
We have our own employees, but do have a side sub staff. We keep them busy. We pay $75.00 per sq., $7.00 per lf chimney flashing, $15.00 per sheet wood decking, we buy all materials and disposal. On larger jobs, 60+ squares and walkable, we pay out $70.00 per sq. I have a sub doing a 67sq, 10/12 roof right now and am paying $110.00 per sq. I have been using this sub for 6 years and have never had a call back. And the main guy drives 1 of my trucks.


I need to work for you too....next year


Top
 Profile  
 
  Post subject:
PostPosted: Thu Oct 07, 2010 5:13 am 
Offline

Joined: Thu Oct 07, 2010 4:53 am
Posts: 3
Location: Huntsville AL
Post liked: 0 time
Liked posts: 0 time
The variations are locally specific. Around Huntsville AL it is labor only. No material, and I typically pay $40-$60/square to my crews. That does include picking up and delivering the shingles and hauling off the old shingle waste.

http://www.smarthomesllc.net

_________________
Smart Homes @ Smart Prices


Top
 Profile  
 
  Post subject:
PostPosted: Thu Oct 07, 2010 10:52 am 
Offline

Joined: Wed Aug 05, 2009 2:30 pm
Posts: 296
Location: Kouts,IN
Post liked: 2 times
Liked posts: 6 times
Reasons for hiring a sub include increasing production, less production management for the company, avoiding payroll tax burdens and cheating on insurance.

The contractor who is simply trying to maintain production and quality, seems to be willing to pay more to avoid cutting corners.

The pimps who practically dominate residential roofing are simply trying to avoid payroll/ comp burdens.... (hell any real business expense that might cause them to actually price a job and sell it) and will seemingly pay much less.

In the end quality on all sides pay ..... customer, contractor and sub contractor

_________________
www.nwiroofleaksandrepairs.com

www.amarcoroofing.com


Top
 Profile  
 
  Post subject:
PostPosted: Thu Oct 07, 2010 10:38 pm 
Offline

Joined: Tue Jul 01, 2008 10:02 pm
Posts: 1260
Location: Wisconsin
Post liked: 25 times
Liked posts: 63 times
Yeah I would never subcontract work for 60 a square. That would cost me money by the end of it.

I am fortunate that I am sub-contracting some work for a guy who has a very good reputation. 13 years, zero recorded complaints, no late payments to suppliers or anything so he pays fairly well when all is said and done because he cares about the work being done. He also inspects each roof of his that gets done a week and does a final walk through with each homeowner. Its about 7-10 houses a week.


Top
 Profile  
 
  Post subject:
PostPosted: Fri Oct 08, 2010 3:01 am 
Offline

Joined: Mon Aug 23, 2010 4:53 pm
Posts: 141
Location: Ohio
Post liked: 0 time
Liked posts: 0 time
Abel wrote:
PTROOFING wrote:
We have our own employees, but do have a side sub staff. We keep them busy. We pay $75.00 per sq., $7.00 per lf chimney flashing, $15.00 per sheet wood decking, we buy all materials and disposal. On larger jobs, 60+ squares and walkable, we pay out $70.00 per sq. I have a sub doing a 67sq, 10/12 roof right now and am paying $110.00 per sq. I have been using this sub for 6 years and have never had a call back. And the main guy drives 1 of my trucks.


I need to work for you too....next year


Common down. I need you and your crew!


Top
 Profile  
 
Display posts from previous:  Sort by  
Post new topic Reply to topic  [ 14 posts ] 


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Jump to:  


Disclaimer

The information and advice provided by the community are for informational purposes only. The site owner and users assume no liability for any errors or misunderstanding in the content, or for any actions taken in reliance thereon. Before making any decisions or taking any action, it is recommended that you consult with a local roofing professional or building official. Roofing can be hazardous. Make sure you protect yourself by using all the appropriate safety procedures.